We operate Poole Bridge and Twin Sails Bridge to help vessels pass safely through the harbour.
How bridge lifts work
The bridges will open one at a time. The first bridge will open, followed by the second. This allows vessels to continue their journey and vessels travelling in the opposite direction to pass. The first bridge will then open again to allow vessels in the basin to continue their journey.
Requesting a bridge lift
To request a bridge lift, you must use VHF channel 12 to contact the Bridge Operator 5 minutes before the lift. This ensures the operator has enough time to change the signal. Failure to contact the operator ahead of time may result in a missed lift.
When requesting a bridge lift you must also:
- be on station and visible
- be ready to pass through
The bridges will only lift on request.
Bridge opening order by time of day
The order the bridges open depends on the time of day.
From 5:30am to 2:30pm:
- Twin Sails Bridge opens first
- Poole Bridge opens immediately afterwards
From 3:30pm to 11:30pm:
- Poole Bridge opens first
- Twin Sails opens immediately afterwards
If vessels are not waiting at the scheduled bridge but there are vessels waiting at the other bridge then that bridge will lift first.
Bridge lifting schedule
Unscheduled lifts
When hourly lifts are scheduled, the only unscheduled lifts will be under the direction of the Harbour Master, or from commercial vessels less than 40 metres.
Complete our online form to apply for an unscheduled lift.
Mariners need to check the headroom displays at the bridge to judge if they can pass below without the bridge being lifted.